Stronger Environmental Monitoring Needed For Onshore Wind Projects: AG

Stronger Environmental Monitoring Needed For Onshore Wind Projects: AG

For release November 17 – Nova Scotia’s Department of Environment and Climate Change needs to act now to improve how it administers and monitors environmental assessments for onshore wind energy projects, Auditor General Kim Adair says in a new report.

The Province is relying on onshore wind energy development to help achieve its 2030 renewable energy targets, making effective environmental assessment and oversight increasingly important, says the AG.

"Environmental impacts should be identified and assessed before a project begins, and approved projects should be monitored to ensure environmental risks are appropriately managed," says Adair.

The audit examined the Province’s environmental assessment process for onshore wind energy projects, focusing on the projects that received approval between 2023 and 2025.

In Nova Scotia, the Minister of Environment and Climate Change is responsible for making environmental assessment decisions for onshore wind energy projects.

The audit found information relevant to the Minister's decision was not always included in briefing materials and decision options. In addition, comments from government reviewers were not consistently reflected in project approval terms and conditions.

We found project owner applications included all required elements, and reviews conducted by the Department were completed within the legislated 50-day timeline.

"While the overall process aligns with practices in other provinces, we found weaknesses that could limit the effectiveness of environmental assessments and post-approval oversight," Adair said.

Audit testing of approved projects revealed approval terms and conditions often lacked measurable criteria and deadlines, and the Department did not adequately monitor projects after approval, including verifying compliance with environmental risk management.

The audit includes 13 recommendations intended to ensure the Minister can make a fully informed decision when approving onshore wind energy projects, and project owners comply with terms and conditions attached to approval decisions. The Department accepted all recommendations.

Ministerial decisions to approve or reject individual projects were outside the scope of the audit.